Market Notices

114644RESERVE NOTICE13/02/2024 04:15:16 PM

Cancellation of Actual (LOR2) condition in the VIC region - 13/02/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR2) condition in the VIC region - 13/02/2024

The Actual LOR2 Condition in the VIC Region advised in AEMO Electricity Market Notice No.114589 is cancelled at 1614 hrs 13/02/2024.

Manager NEM Real Time Operations
     
114607LOAD SHED13/02/2024 02:35:06 PM

Load Shedding Direction in the Vic Region

AEMO ELECTRICITY MARKET NOTICE

Load Shedding Direction in the Vic Region

AEMO has directed load shedding commencing at 1420 hrs 13/02/2024
in the Victoria region to restore power system security.

The direction was issued under section 116 of the NEL, and was a clause 4.8.9 instruction under the NER.

Manager NEM Real Time Operations
     
112364RESERVE NOTICE14/12/2023 06:16:35 PM

Cancellation of Actual (LOR2) condition in the NSW region - 14/12/2023

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR2) condition in the NSW region - 14/12/2023

The Actual LOR2 Condition in the NSW Region advised in AEMO Electricity Market Notice No.112362 is cancelled at 1810 hrs 14/12/2023.

Manager NEM Real Time Operations
112362RESERVE NOTICE14/12/2023 06:00:52 PM

Actual Lack Of Reserve Level 2 (LOR2) in the NSW region - 14/12/2023

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 2 (LOR2) in the NSW region - 14/12/2023

An Actual LOR2 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR2 condition is not forecast in Pre Dispatch

The capacity reserve required is 690 MW
The minimum reserve available is 678 MW

AEMO is seeking an immediate market response.

An insufficient market response may require AEMO to implement a AEMO intervention event.

Manager NEM Real Time Operations
110560RESERVE NOTICE27/10/2023 08:20:02 PM

Cancellation of Actual (LOR2) condition in the SA region - 27/10/2023

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR2) condition in the SA region - 27/10/2023

The Actual LOR2 Condition in the SA Region advised in AEMO Electricity Market Notice No.110559 is cancelled at 2015 hrs 27/10/2023.

Manager NEM Real Time Operations
110559RESERVE NOTICE27/10/2023 07:49:02 PM

Actual Lack Of Reserve Level 2 (LOR2) in the SA region - 27/10/2023

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 2 (LOR2) in the SA region - 27/10/2023

An Actual LOR2 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the SA region from 1930 hrs.
The Actual LOR2 condition is not forecast in Pre Dispatch

The capacity reserve required is 480 MW
The minimum reserve available is 465 MW

AEMO is seeking an immediate market response.

An insufficient market response may require AEMO to implement a AEMO intervention event.

Manager NEM Real Time Operations
108172RESERVE NOTICE25/05/2023 08:46:48 PM

Update - PDPASA - Cancellation of the Actual Lack Of Reserve Level 2 (LOR2) in the NSW Region on 25/05/2023

AEMO ELECTRICITY MARKET NOTICE

The Actual LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 108160 is cancelled at 2045 hrs 25/05/2023.

Manager NEM Real Time Operations
108165RESERVE NOTICE25/05/2023 08:45:53 PM

PDPASA - Cancellation of the Actual Lack Of Reserve Level 2 (LOR2) in the NSW Region on 25/05/2023

AEMO ELECTRICITY MARKET NOTICE

The Actual LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 108160 is cancelled at 2145 hrs 25/05/2023.

Manager NEM Real Time Operations
108160RESERVE NOTICE25/05/2023 08:19:28 PM

Actual Lack Of Reserve Level 2 (LOR2) in the NSW Region on 25/05/2023

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 2 (LOR2) in the NSW region - 25/05/2023

An Actual LOR2 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 2000 hrs.

The Actual LOR2 condition is forecast to exist until 2030 hrs.

The forecast capacity reserve requirement is 851 MW.
The minimum capacity reserve available is 767 MW.

AEMO is seeking an immediate market response.

An insufficient market response may require AEMO to implement an AEMO intervention event.