Market Notices

80999RESERVE NOTICE10/12/2020 10:44:57 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 10/12/2020

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 10/12/2020

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 2240 hrs.
The Actual LOR1 condition is forecast to exist until hrs.

The capacity reserve requirement is 1300 MW
The minimum capacity reserve available is 944 MW

Manager NEM Real Time Operations
80989RESERVE NOTICE10/12/2020 02:20:34 PM

Cancellation of Actual (LOR1) condition in the NSW region - 10/12/2020

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 10/12/2020
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No80988 is cancelled at 1415 hrs 10/12/2020].

Manager NEM Real Time Operations
80988RESERVE NOTICE10/12/2020 01:52:09 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 10/12/2020

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 10/12/2020

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for theNSW region from 1345 hrs.
The Actual LOR1 condition is forecast to exist until 1400 hrs.

The capacity reserve requirement is 1360 MW
The minimum capacity reserve available is 1322 MW

Manager NEM Real Time Operations
80604RESERVE NOTICE01/12/2020 06:06:31 PM

Cancellation of Actual (LOR1) condition in the NSW region - 29/11/2020

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 01/12/2020

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice 80602 is cancelled at 1805 hrs 01/12/2020.

Manager NEM Real Time Operations
80602RESERVE NOTICE01/12/2020 05:32:46 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 01/12/2020

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 01/12/2020

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs.

The capacity reserve requirement is 1447 MW
The minimum capacity reserve available is 1340 MW

Manager NEM Real Time Operations
80503RESERVE NOTICE29/11/2020 05:10:49 PM

Cancellation of Actual (LOR1) condition in the NSW region - 29/11/2020

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 29/11/2020

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice 80502 is cancelled at 1710 hrs 29/11/2020.

Manager NEM Real Time Operations
80502RESERVE NOTICE29/11/2020 04:59:41 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 29/11/2020

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 29/11/2020

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1655 hrs.
The Actual LOR1 condition is forecast to exist until 1730 hrs.

The capacity reserve requirement is 1320 MW
The minimum capacity reserve available is 1162 MW

Manager NEM Real Time Operations
80429RESERVE NOTICE28/11/2020 05:22:05 PM

Cancellation of Actual (LOR1) condition in the NSW region - 28/11/2020

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 28/11/2020

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.80420 is cancelled at 1720 hrs 28/11/2020.

Manager NEM Real Time Operations
80420RESERVE NOTICE28/11/2020 05:01:48 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 28/11/2020

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 28/11/2020

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1655 hrs.
The Actual LOR1 condition is forecast to exist until 1800 hrs.

The capacity reserve requirement is 1320 MW
The minimum capacity reserve available is 1286 MW

Manager NEM Real Time Operations