Market Notices

101147RESERVE NOTICE18/08/2022 06:51:42 AM

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 18/08/2022

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 18/08/2022

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 0630 hrs.

The Actual LOR1 condition is forecast to exist until 0730 hrs.
The forecast capacity reserve requirement is 639 MW.
The minimum capacity reserve available is 566 MW.

Manager NEM Real Time Operations
101058RESERVE NOTICE16/08/2022 08:20:54 PM

Cancellation of Actual (LOR1) condition in the QLD region - 16/08/2022

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the QLD region - 16/08/2022

The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.101013 is cancelled at 2015 hrs 16/08/2022.

Manager NEM Real Time Operations
101057RESERVE NOTICE16/08/2022 08:17:32 PM

Cancellation of Actual Lack Of Reserve Level 1 (LOR1) in the SA Region on 16/08/2022

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the SA region - 16/08/2022
.
The Actual LOR1 Condition in the SA Region advised in AEMO Electricity Market Notice No.101056 is cancelled at 2015 hrs 16/08/2022

Manager NEM Real Time Operations
101056RESERVE NOTICE16/08/2022 07:45:58 PM

Actual Lack Of Reserve Level 1 (LOR1) in the SA Region on 16/08/2022

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 16/08/2022

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the SA region from 1930 hrs.

The Actual LOR1 condition is forecast to exist until 2030 hrs.

The forecast capacity reserve requirement is 600 MW.
The minimum capacity reserve available is 541 MW.


Manager NEM Real Time Operations
101051RESERVE NOTICE16/08/2022 05:47:25 PM

Actual Lack Of Reserve Level 1 (LOR1) in the QLD Region on 16/08/2022

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 16/08/2022

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1730 hrs.

The Actual LOR1 condition is forecast to exist until 2200 hrs.

The forecast capacity reserve requirement is 666 MW.
The minimum capacity reserve available is 482 MW.


Manager NEM Real Time Operations
101013RESERVE NOTICE16/08/2022 07:42:02 AM

Cancellation of Actual (LOR1) condition in the QLD region - 16/08/2022

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the QLD region - 16/08/2022

The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.101012 is cancelled at 0730 hrs 16/08/2022.

Manager NEM Real Time Operations
101012RESERVE NOTICE16/08/2022 06:46:16 AM

Actual Lack Of Reserve Level 1 (LOR1) in the QLD Region on 16/08/2022

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 16/08/2022

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 0630 hrs.

The Actual LOR1 condition is forecast to exist until 0730 hrs.

The forecast capacity reserve requirement is 800 MW.
The minimum capacity reserve available is 794 MW.


Manager NEM Real Time Operations
100993RESERVE NOTICE15/08/2022 06:39:39 PM

Cancellation of Actual (LOR1) condition in the QLD region - 15/08/2022

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the QLD region - 15/08/2022

The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.100992 is cancelled at 1830 hrs 15/08/2022.

Manager NEM Real Time Operations
100992RESERVE NOTICE15/08/2022 05:49:12 PM

Actual Lack Of Reserve Level 1 (LOR1) in the QLD Region on 15/08/2022

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 15/08/2022

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1730 hrs.

The Actual LOR1 condition is forecast to exist until 1930 hrs.
The forecast capacity reserve requirement is 906 MW.
The minimum capacity reserve available is 771 MW.


Manager NEM Real Time Operations