Inter-Regional Transfer limit variation - Murraylink
Inter-Regional Transfer limit variation - Murraylink
There has been an unplanned outage of the Murraylink interconnector.
The following constraint set was invoked at 0610 hrs 03/09/2023
I-MURAYLINK
The constraint set contains the following interconnectors on the left hand side.
V-S-MNSP1
VIC1-NSW1
Refer to AEMO Network Outage Scheduler (NOS) for further details.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - LeFevre 6576 275 kV CB- SA region - 25/08/2023
Inter-regional transfer limit variation - LeFevre 6576 275 kV CB- SA region - 25/08/2023
At 1730 hrs 25/08/2023 there was a short notice outage of the LeFevre 6576 275 kV CB, de-loading the Pelican Point - Lefevre 275 kV line.
The following constraint set(s) invoked at 1730 hrs 25/08/2023:
S-LFPP_PELPT
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-Regional Transfer limit variation - Directlink - NSW Region
Inter-Regional Transfer limit variation - Directlink - NSW Region
There has been an unplanned outage of all three Legs of Directlink .
The following constraint set was invoked at 1240 hrs 25/08/2023
N-X_MBTE_3
The constraint set contains the following interconnector on the left hand side.
N-Q-MNSP1
Refer AEMO Network Outage Scheduler (NOS) for further details.
Manager NEM Real Time Operations
Inter-Regional Transfer limit variation - Directlink - NSW Region
Inter-Regional Transfer limit variation - Directlink - NSW Region
There has been an unplanned outage of the No.2 and No.3 Legs of Directlink .
The following constraint set was invoked at 0825 hrs 25/08/2023
N-X_MBTE_3
The constraint set contains the following interconnector on the left hand side.
N-Q-MNSP1
Refer AEMO Network Outage Scheduler (NOS) for further details.
Manager NEM Real Time Operations
Inter-regional transfer limit variation: Middle Ridge - Greenbank No 8848 275 kV Line (Qld) - Voltage Control
Inter-regional transfer limit variation: Middle Ridge - Greenbank No 8848 275 kV Line (Qld) - Voltage Control
Middle Ridge - Greenbank No 8848 275 kV Line has been de-energised to manage voltages in the Queensland region.
The following constraint set was invoked at 0400 hrs 19/08/2023
Q-MRGB_8848_8849
The constraint set contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
NSW1-QLD1
Refer to AEMO Network Outage Scheduler (NOS) for further details
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Tamworth SVC - NSW region - 18/08/2023
Inter-regional transfer limit variation - Tamworth SVC - NSW region - 18/08/2023
At 1820 hrs 18/08/2023 there was a short notice outage of the Tamworth SVC.
The following constraint set(s) invoked at 1820 hrs 18/08/2023
N-TW_SVC and N-X_LS+TW_SVC
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Tamworth No.1 330 kV SVC- NSW region - 17/08/2023
Inter-regional transfer limit variation - Tamworth No.1 330 kV SVC- NSW region - 17/08/2023
At 1727 hrs 17/08/2023 there was an unplanned outage of Tamworth No.1 330 kV SVC.
The following constraint set(s) invoked at 1740 hrs 17/08/2023
N-TW_SVC
N-X_LS+TW_SVC
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MSNP1
NSW1-QLD1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - SESS CB6611 - SA region - 14/08/2023
Inter-regional transfer limit variation - SESS CB6611 - SA region - 14/08/2023
At 1630 hrs 14/08/2023 there is a short notice outage of SESS CB6611.
The following constraint set(s) invoked at 1630 hrs 14/08/2023
S-SECB6611_10_BC-2CP
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Update - Inter-regional transfer limit variation - Georgetown - Comalco No 5 220kV Line - TAS region - 14/08/2023
Update - Inter-regional transfer limit variation - Georgetown - Comalco No 5 220kV Line - TAS region - 14/08/2023
At 0850 hrs 14/08/2023 there was an unplanned outage of Georgetown - Comalco No 5 220kV Line.
The following constraint set(s) invoked at 0900 hrs 14/08/2023
F-T-CSGO
This constraint set(s) contains equations with the following interconnectors on the LHS.
T-V-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations