74990RECLASSIFY CONTINGENCY19/03/2020 09:00:50 PM

Reclassification of a Non-Credible Contingency Event: Hazelwood - Rowville No.1 220kV line and Hazelwood - Rowville No.2 220kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: VIC1

Lines: Hazelwood - Rowville No.1 220kV and Hazelwood - Rowville No.2 220kV

Duration: 19/03/2020 21:00 until further notice

Constraint set(s) invoked:
V-HWRO_R_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Auto-generated on behalf of Manager NEM Real Time Operations
74989MARKET INTERVENTION19/03/2020 04:45:26 PM

Cancellation - AEMO Intervention Event - Intervention price dispatch intervals - Direction SA region 18/03/2020

AEMO ELECTRICITY MARKET NOTICE

Refer Market Notices 74974

The AEMO Intervention Event and all associated directions are cancelled from 1600 hrs 19/03/2020.

Manager NEM Real Time Operations
74987CONSTRAINTS19/03/2020 01:03:38 PM

Revised System Strength limits in North Queensland

AEMO ELECTRICITY MARKET NOTICE

AEMO and Powerlink are continuing to investigate system strength requirements in North Queensland.

Through this work, AEMO and Powerlink have identified the need, depending on power system conditions, to constrain the output of three generators in North Queensland to maintain power system security.

The constraint equation is expected to limit generation from the three generators depending on power system conditions. The generators are Mt Emerald Wind Farm, Haughton Solar Farm and Sun Metals Solar Farm.

The constraint equations are: Q_NIL_STRGTH_MEWF, Q_NIL_STRGTH_HAUSF, Q_NIL_STRGTH_SMSF. These will be implemented at 1500hrs EST today.

The minimum generator combinations and limits are:
1 - 3 x Stanwell, 1 x Callide B, 1 x Callide C, 4 x Gladstone, 10 x Total Stanwell+Callide+Gladstone, 4 x Kareeya, 2 x Barron Gorge: 100% output
2 - 3 x Stanwell, 1 x Callide B, 1 x Callide C, 4 x Gladstone, 10 x Total Stanwell+Callide+Gladstone, 4 x Kareeya, 1 x Barron Gorge: 80% output
3 - 3 x Stanwell, 1 x Callide B, 1 x Callide C, 4 x Gladstone, 10 x Total Stanwell+Callide+Gladstone, 2 x Kareeya, 1 x Townsville GT: 80% output
4 - 3 x Stanwell, 1 x Callide B, 1 x Callide C, 4 x Gladstone, 10 x Total Stanwell+Callide+Gladstone, 2 x Kareeya, 1 x Barron Gorge: 70% output
5 - 3 x Stanwell, 1 x Callide B, 1 x Callide C, 4 x Gladstone, 10 x Total Stanwell+Callide+Gladstone, 4 x Kareeya: 70% output

If these combinations are not met all three generators have a limit of 0 MW and 0 inverters.

For further details please contact James Lindley at james.lindley@aemo.com.au or Simon Taylor at businessdevelopment@powerlink.com.au

Ben Blake
AEMO Operations
74986PRICES UNCHANGED19/03/2020 08:31:42 AM

[EventId:202003190805_confirmed] Prices for interval 19-Mar-2020 08:05 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0830 hrs on 19 March 2020

PRICES ARE NOW CONFIRMED for dispatch interval 19-Mar-2020 08:05.

In accordance with Market Notice 74975 AEMO has reviewed this dispatch interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
74985PRICES UNCHANGED19/03/2020 08:31:17 AM

[EventId:202003190830_confirmed] Prices for interval 19-Mar-2020 08:30 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0830 hrs on 19 March 2020

PRICES ARE NOW CONFIRMED for dispatch interval 19-Mar-2020 08:30.

In accordance with Market Notice 74980 AEMO has reviewed this dispatch interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
74984PRICES UNCHANGED19/03/2020 08:32:04 AM

[EventId:202003190825_confirmed] Prices for interval 19-Mar-2020 08:25 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0830 hrs on 19 March 2020

PRICES ARE NOW CONFIRMED for dispatch interval 19-Mar-2020 08:25.

In accordance with Market Notice 74979 AEMO has reviewed this dispatch interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
74983PRICES UNCHANGED19/03/2020 08:30:57 AM

[EventId:202003190820_confirmed] Prices for interval 19-Mar-2020 08:20 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0830 hrs on 19 March 2020

PRICES ARE NOW CONFIRMED for dispatch interval 19-Mar-2020 08:20.

In accordance with Market Notice 74978 AEMO has reviewed this dispatch interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
74982PRICES UNCHANGED19/03/2020 08:30:34 AM

[EventId:202003190815_confirmed] Prices for interval 19-Mar-2020 08:15 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0830 hrs on 19 March 2020

PRICES ARE NOW CONFIRMED for dispatch interval 19-Mar-2020 08:15.

In accordance with Market Notice 74977 AEMO has reviewed this dispatch interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
74981PRICES UNCHANGED19/03/2020 08:30:17 AM

[EventId:202003190810_confirmed] Prices for interval 19-Mar-2020 08:10 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0830 hrs on 19 March 2020

PRICES ARE NOW CONFIRMED for dispatch interval 19-Mar-2020 08:10.

In accordance with Market Notice 74976 AEMO has reviewed this dispatch interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.