74975PRICES SUBJECT TO REVIEW19/03/2020 08:00:15 AM

[EventId:202003190805_review] Prices for interval 19-Mar-2020 08:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0800 hrs on 19 March 2020

PRICES ARE SUBJECT TO REVIEW for dispatch interval 19-Mar-2020 08:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
74974MARKET INTERVENTION18/03/2020 06:02:11 PM

Direction - SA Region - 18/03/2020

AEMO ELECTRICITY MARKET NOTICE.

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).

The direction was necessary to maintain the power system in a secure operating state.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

The issue of the direction commences an AEMO intervention event.

AEMO declares all dispatch intervals during the event to be intervention dispatch intervals, commencing from the interval ending 1805 hrs on 18/03/2020.

Intervention pricing does not apply to this AEMO intervention event.


Manager NEM Real Time Operations
74972INTER-REGIONAL TRANSFER18/03/2020 04:18:09 PM

Inter-regional transfer limit variation - Lismore SVC - NSW region - 18 March 2020

AEMO ELECTRICITY MARKET NOTICE

At 1539 hrs 18/03/2020 there was an unplanned outage of the Lismore SVC.

The following constraint set invoked at 1545 hrs

N-LS_VC1

This constraint set contains equations with the following interconnectors on the LHS.

N-Q-MNSP1
NSW1-QLD1


Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
74971MARKET INTERVENTION18/03/2020 03:28:17 PM

Possible intervention to manage power system security in South Australia (SA) Region

AEMO ELECTRICITY MARKET NOTICE

The synchronous generating units expected to be synchronised in SA from 0100 hrs 19/03/2020 to 1530 hrs 19/03/2020 in Pre-dispatch published at 1500 hrs 18/03/2020 are inadequate to maintain sufficient system strength in SA and hence a secure operating state.

AEMO currently estimates that, in the absence of sufficient market response by 1800 hrs 18/03/2020, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
74970RECLASSIFY CONTINGENCY17/03/2020 10:09:10 PM

Cancellation of a Non-Credible Contingency Event: Hazelwood - Rowville No.1 220kV line and Hazelwood - Rowville No.2 220kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: VIC1

Lines: Hazelwood - Rowville No.1 220kV and Hazelwood - Rowville No.2 220kV

Cancellation time: 17/03/2020 22:09

Constraint set(s) revoked:
V-HWRO_R_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Refer AEMO Electricity Market Notice 74969

Auto-generated on behalf of Manager NEM Real Time Operations
74969RECLASSIFY CONTINGENCY17/03/2020 09:07:50 PM

Reclassification of a Non-Credible Contingency Event: Hazelwood - Rowville No.1 220kV line and Hazelwood - Rowville No.2 220kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: VIC1

Lines: Hazelwood - Rowville No.1 220kV and Hazelwood - Rowville No.2 220kV

Duration: 17/03/2020 21:07 until further notice

Constraint set(s) invoked:
V-HWRO_R_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Auto-generated on behalf of Manager NEM Real Time Operations
74968MARKET INTERVENTION17/03/2020 01:34:54 PM

Cancellation - AEMO Intervention Event - Intervention price dispatch intervals - Direction SA region 16/03/2020

AEMO ELECTRICITY MARKET NOTICE

Refer Market Notices 74965

The AEMO Intervention Event and all associated directions are cancelled from 1330 hrs 17/03/2020.

Manager NEM Real Time Operations
74966RESERVE NOTICE17/03/2020 09:34:03 AM

RESERVE NOTICE MT PASA PUBLICATION 17 March 2020

The MTPASA result published on 17 March 2020 identifies no Low Reserve Conditions.

Please note that MTPASA informs the market of potential reliability issues to allow the market to respond in the first instance, potentially avoiding the need for any market intervention or direction from AEMO.

For further information, please refer to:
https://www.aemo.com.au/Electricity/National-Electricity-Market-NEM/Data/Market-Management-System-MMS/Projected-Assessment-of-System-Adequacy

This notice supersedes Market Notice 74862 published on 10 March 2020.

Background
As part of a broader process of implementing the reliability standard, AEMO runs the Medium Term Projected Assessment of System Adequacy (MTPASA) process weekly to forecast expected unserved energy levels over a two year period. If the expected annual unserved energy exceeds the maximum level specified by the Reliability Standard, a Low Reserve Condition is identified.

For more information about how AEMO implements the reliability standard, please view the Reliability Standard Implementation Guidelines (RSIG) available on AEMO's website at
https://www.aemo.com.au/Electricity/National-Electricity-Market-NEM/Planning-and-forecasting/Reliability-Standard-Implementation-Guidelines

Forecasting
AEMO
74965MARKET INTERVENTION16/03/2020 04:06:10 PM

Direction - SA Region - 16/03/2020

AEMO ELECTRICITY MARKET NOTICE.

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).

The direction was necessary to maintain the power system in a secure operating state.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

The issue of the direction commences an AEMO intervention event.

AEMO declares all dispatch intervals during the event to be intervention dispatch intervals, commencing from the interval ending 1610 hrs on 16/03/2020.

Intervention pricing does not apply to this AEMO intervention event.