Market Notices

54910INTER-REGIONAL TRANSFER14/09/2016 08:14:11 AM

New South Wales region 330 kV transmission line outage withdrawn

AEMO ELECTRICITY MARKET NOTICE

Please be advised that the planned outage for today, 14 Sept 16, of the Liddell - Newcastle (81) 330 kV line has been withdrawn by the TNSP.
Constraints are now being adjusted to cater for this change.

Manager NEM Real Time Operations
54909NON-CONFORMANCE14/09/2016 07:35:15 AM

NON-CONFORMANCE Region VIC1 Wednesday, 14 September 2016

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Wednesday, 14 September 2016

AEMO declared a schedule generating unit non-conforming

Unit: MCKAY1
Duration: 14/09/2016 07:30 to 14/09/2016 07:35
Amount: -187 MW
Constraint: NC-V_MCKAY1

Auto-generated on behalf of Manager NEM Real Time Operations
54908GENERAL NOTICE14/09/2016 07:05:09 AM

Victorian region 500 kV transmission line outage withdrawn

AEMO ELECTRICITY MARKET NOTICE
Refer Market Notice 54865

Please be advised that the planned outage for today, 14 Sept 16, of the Moorabool-Mortlake 500kV line has been withdrawn by the TNSP.
Constraints are now being adjusted to cater for this change.

Manager NEM Real Time Operations
54907NON-CONFORMANCE13/09/2016 06:30:11 PM

NON-CONFORMANCE Region VIC1 Tuesday, 13 September 2016

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Tuesday, 13 September 2016

AEMO declared a schedule generating unit non-conforming

Unit: JLB03
Duration: 13/09/2016 18:15 to 13/09/2016 18:30
Amount: -38 MW
Constraint: NC-V_JLB03

Auto-generated on behalf of Manager NEM Real Time Operations
54906RESERVE NOTICE13/09/2016 05:23:29 PM

Cancellation of the Actual (LOR2) condition in the South Australia region - 13 Sept 2016

AEMO ELECTRICITY MARKET NOTICE

Cancellation of the Actual (LOR2) condition in the South Australia region - 13 Sept 2016
Refer to AEMO Electricity Market Notice No. 54897
The Actual LOR2 condition in the South Australia Region is cancelled at 1715 hrs 13 Sept 2016

Manager NEM Real Time Operations
54905GENERAL NOTICE13/09/2016 05:28:04 PM

Queensland regional load variation advice

AEMO ELECTRICITY MARKET NOTICE.

Refer MARKET NOTICE 54904.
AEMO can advise that the Queensland region major industrial load is now in the process of returning to full load.

Manager NEM Real Time Operations
54904GENERAL NOTICE13/09/2016 04:57:53 PM

Queensland region load reduction advice 13 Sept 2016

AEMO ELECTRICITY MARKET NOTICE.

AEMO has become aware of the following circumstance with respect to the power system,
At 1630 hrs a major Industrial load in the Queensland Region has reduced from 920 MW toward 0 MW over a 25 minute period.
An update will be provided as informatoin becomes available.

Manager NEM Real Time Operations

54903MARKET SYSTEMS14/09/2016 12:07:32 PM

CHG0040428: Planned System Change - MSATS Pre-Production Year-End 2016 - Release 46.86 - Stage 1

Change Number: CHG0040428

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: MSATS - Consumer Administration and Transfer Solution

Change Title: Planned System Change - MSATS Pre-Production Year-End 2016 - Release 46.86 - Stage 1

Change Start Date & Time: 21/09/2016 14:00:00 AEST

Change End Date & Time: 21/09/2016 15:00:00 AEST


Outage Start Date & Time:

Outage End Date & Time:


Change Description:

The MSATS Pre-Production system will be upgraded with Release 46.86 Stage 1, pre-release data update, as per the release schedule 933A issued on 12th August 2016.
Note: There are no schema changes associated with this release

Environment: Pre-Production

Participant Impact and Requirements:

Awareness of this change. There is no outage. MSATS Pre-Production environment will be available during the change times mentioned above.

Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
54902MARKET SYSTEMS14/09/2016 12:06:55 PM

CHG0040415:Planned System Upgrade to EMMS Pre-Production

Change Number: CHG0040415

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: Electricity Market Management System

Change Title: Planned System Upgrade to EMMS Pre-Production

Change Start Date & Time: 21/09/2016 09:00:00 AEST

Change End Date & Time: 21/09/2016 15:00:00 AEST


Outage Start Date & Time:

Outage End Date & Time:


Change Description:

The EMMS Pre-Production will be updated to increase the stability, reliability and security.

Environment: Pre-Production

Participant Impact and Requirements:

Awareness of this maintenance. Client connection to EMMS Preprod Participant Server will be disconnected, then connected again in few minutes, no data loss expected. The is no other impact.

Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600