CHG0058729 : Planned Maintenance on EMMS Pre-Production
Change Number: CHG0058729
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Electricity Market Management System
Change Title: Planned Maintainence on EMMS Pre-Production
Change Start Date & Time: 07/04/2020 08:00:00 AEST
Change End Date & Time: 09/04/2020 17:00:00 AEST
Outage Start Date & Time: 07/04/2020 09:00:00 AEST
Outage End Date & Time: 07/04/2020 11:00:00 AEST
Change Description:
Planned Maintainence on EMMS Pre-Production
Environment: Pre-Production
Participant Impact and Requirements:
EMMS Pre-Production environment will not be available during the outage period to allow maintenance activities
Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
Cancellation - Reclassification of a Non-Credible Contingency Event: Gordon - Chapel Street No.1 and No.2 220 kV lines in Tasmania. Bushfire.
Cancellation - Reclassification of a Non-Credible Contingency Event: Gordon - Chapel Street No.1 and No.2 220 kV lines in Tasmania. Bushfire.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Bushfire.
AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any Bushfire activity in the vicinity of the following lines. Accordingly, its classification has reverted to a non-credible contingency event.
Region: TAS Region
Lines: Gordon - Chapel Street No.1 and No.2 220 kV lines
Cancellation time: 0845 hrs 02/04/2020
Constraint set(s) F-T-CSGO and T-CSGO_N-2 revoked: 0845 hrs
Refer AEMO Electricity Market Notice 67914
Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Gordon - Chapel Street No.1 and No.2 220 kV lines in Tasmania. Bushfire.
Reclassification of a Non-Credible Contingency Event: Gordon - Chapel Street No.1 and No.2 220 kV lines in Tasmania. Bushfire.
Reclassification of a non-credible contingency event as a credible contingency event due to Bushfire. (Planned burn off)
AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly, AEMO has reclassified it as a credible contingency event.
Region: TAS
Lines: Gordon - Chapel Street No.1 and No.2 220 kV lines
Duration: 0820 hrs 02/04/2020 until further notice
Constraint set(s) invoked: F-T-CSGO and T-CSGO_N-2
Manager NEM Real Time Operations
Update - Non-credible contingency event - SA region - 01/04/2020
At 1541 hrs at Snuggery 132kV Gen Bus tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
Non-credible contingency event - SA region - 01/04/2020
At 1541 hrs at Snuggery 132kV Gen Bus tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
CHG0058351: UPDATE - PROD - 5MS - Release 1 - Reallocations
Change Number: CHG0058351
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: EMMS - Settlements, EMMS - Billing
Change Title: PROD - 5MS - Release 1 - Reallocations
Change Start Date & Time: 30/03/2020 08:00:00 AEST
Change End Date & Time: 02/04/2020 18:00:00 AEST
Outage Start Date & Time: 01/04/2020 13:00:00 AEST
Outage End Date & Time: 01/04/2020 14:00:00 AEST
Change Description:
The Reallocations functionality for 5MS will be deployed in the AEMO Production environment on Wednesday 1 April 2020.
Environment: Production
Participant Impact and Requirements:
The new functionality will allow for those Market Participants that are registered for reallocations to submit reallocations for the period after 1 July 2021 in five-minute intervals.
EMMS 5MS Technical Specification - Reallocations is the relevant Technical Specification for the deployment and is available on our website.
https://aemo.com.au/-/media/files/electricity/nem/it-systems-and-change/2019/emms-technical-specification-5ms-reallocations.pdf
Market Participants will also experience a new User Interface and new APIs to submit reallocations and new alert and notification features. Some other enhancements include: bulk edit, CSV download or upload capability, public holidays, and reversing or duplicating reallocations.
Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0058725: Planned System Maintenance - Electricity MMS PreProduction
Change Number: CHG0058725
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Electricity Market Management System
Change Title: Planned System Maintenance - Electricity MMS PreProduction
Change Start Date & Time: 06/04/2020 13:00:00 AEST
Change End Date & Time: 06/04/2020 15:00:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Change Description:
Maintenance is performed on the EMMS PreProduction environment.
Environment: Pre-Production
Participant Impact and Requirements:
The maintenance activity is not expected to have any impact on the pre-production environment, and therefore if any issue is identified after the maintenance activity it should be reported to AEMO.
Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
Cancellation - Inter-regional transfer limit variation: Hazelwood - South Morang No.2 500 kV Line (Vic) - Voltage Control
Cancellation - Inter-regional transfer limit variation: Hazelwood - South Morang No.2 500 kV Line (Vic) - Voltage Control
Refer AEMO Electricity Market Notice 75090
The Hazelwood - South Morang No.2 500 kV Line has been returned to service.
The following constraint set was revoked at 0510 hrs 01/04/2020.
V-HWSM
The constraint set contains equations with the following interconnectors on the LHS.
T-V-MNSP1
V-S-MNSP1
V-SA
VIC1-NSW1
Manager NEM Real Time Operations
Inter-regional transfer limit variation: Hazelwood - South Morang No 2 500 kV Line (VIC) - Voltage Control
The Hazelwood - South Morang No 2 500 kV Line has been de-energised to manage voltages in the Victoria region.
The following constraint set was invoked at 0205 hrs 01/04/2020
V-HWSM
The constraint set contains equations with the following interconnectors on the LHS.
T-V-MNSP
V-S-MNSP1
V-SA
VIC1-NSW1
Refer to AEMO Network Outage Scheduler (NOS) for further details
Manager NEM Real Time Operations