116056MARKET INTERVENTION09/04/2024 02:48:54 PM

Update - Possible intervention to manage power system security in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Possible intervention to manage power system security in SA region

Refer AEMO Electricity Market Notice 116054

The synchronous generating units currently expected to be synchronised in SA from 1030 hrs 10/04/2024 will be inadequate to maintain a secure operating state in SA .

AEMO estimates that, in the absence of sufficient market response by 1600 hrs 09/04/2024, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
     
116055RECLASSIFY CONTINGENCY09/04/2024 12:45:55 PM

Reclassification of a Non-Credible Contingency Event: Bannaby - Mt Piper 5A6 500kV line and Bannaby - Mt Piper 5A7 500kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: NSW1

Lines: Bannaby - Mt Piper 5A6 500kV and Bannaby - Mt Piper 5A7 500kV

Duration: 09/04/2024 12:45 until further notice

Constraint set(s) invoked:
N-5A6+5A7_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1
VIC1-NSW1


Auto-generated on behalf of Manager NEM Real Time Operations
     
116054MARKET INTERVENTION09/04/2024 12:45:18 PM

Possible intervention to manage power system security in SA region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in SA region

The synchronous generating units currently expected to be synchronised in SA from 0830 hrs 10/04/2024 will be inadequate to maintain a secure operating state in SA .
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA .

Manager NEM Real Time Operations
     
116053RESERVE NOTICE09/04/2024 01:53:38 PM

RESERVE NOTICE MT PASA PUBLICATION 9 April 2024

The MTPASA result published on 9 April 2024 identifies Low Reserve Conditions as annual unserved energy exceeds the Reliability Standard between:
-- April 2025 - April 2026 in New South Wales.

AEMO declares low reserve conditions in accordance with clause 4.8.4 of the National Electricity Rules for the following region(s) and periods:
-- November 2025 - March 2026 in New South Wales when forecast demand exceeds supply under some circumstances.

Please note that MTPASA informs the market of potential reliability issues to allow the market to respond in the first instance, potentially avoiding the need for any AEMO intervention.

For further information, please refer to:
https://www.aemo.com.au/Electricity/National-Electricity-Market-NEM/Data/Market-Management-System-MMS/Projected-Assessment-of-System-Adequacy

This notice supersedes Market Notice 115924 published on 2 April 2024.

Background
As part of a broader process of implementing the reliability standard, AEMO runs the Medium Term Projected Assessment of System Adequacy (MTPASA) process weekly to forecast expected unserved energy levels over a two year period. If the expected annual unserved energy exceeds the maximum level specified by the Reliability Standard, a Low Reserve Condition is identified.

For more information about how AEMO implements the reliability standard, please view the Reliability Standard Implementation Guidelines (RSIG) available on AEMO's website at https://www.aemo.com.au/Electricity/National

Forecasting
AEMO
     
116052GENERAL NOTICE09/04/2024 11:26:28 AM

Increase to QNI limit to next hold point of 850 MW NSW to Qld

AEMO ELECTRICITY MARKET NOTICE

Refer to market notices 114742.

AEMO, TransGrid, Powerlink have reviewed the test results following the QNI minor testing on 15th February 2024. The next hold point can now be released.

The hold point of 850 MW from NSW to Qld will be implemented as of 1000 hrs 10th April 2024.

Please also refer to the published formal QNI minor testing information at the following link:
https://www.aemo.com.au/consultations/current-and-closed-consultations/qld-to-nsw-interconnector-qni-upgrade

Ben Blake
AEMO Operations
     
116050MARKET INTERVENTION08/04/2024 04:00:02 PM

Update - Direction - SA Region - 07/04/2024

AEMO ELECTRICITY MARKET NOTICE

Update - Direction - SA Region - 07/04/2024

Refer Market Notice 116026

The AEMO intervention event that commenced from interval ending 1705 hrs on 07/04/2024 is continuing.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

Manager NEM Real Time Operations
     
116047NON-CONFORMANCE08/04/2024 03:05:14 PM

NON-CONFORMANCE Region QLD1 Monday, 8 April 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Monday, 8 April 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 08/04/2024 15:00 to 08/04/2024 15:05
Amount: -43 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
116044PRICES UNCHANGED08/04/2024 01:14:39 PM

[EventId:202404081245_confirmed] Prices for interval 08-Apr-2024 12:45 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1310 hrs on 8 April 2024

PRICES ARE NOW CONFIRMED for trading interval 08-Apr-2024 12:45.

In accordance with Market Notice 116032 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
116043PRICES UNCHANGED08/04/2024 01:13:44 PM

[EventId:202404081310_confirmed] Prices for interval 08-Apr-2024 13:10 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1310 hrs on 8 April 2024

PRICES ARE NOW CONFIRMED for trading interval 08-Apr-2024 13:10.

In accordance with Market Notice 116038 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm