Market Notices

82200RECLASSIFY CONTINGENCY17/01/2021 02:41:30 PM

Reclassification of a Non-Credible Contingency Event: Tarong - Chinchilla No.7168 132 kV line and Tarong - Chinchilla No.7183 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Tarong - Chinchilla No.7168 132 kV and Tarong - Chinchilla No.7183 132 kV

Duration: 17/01/2021 14:41 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
82197INTER-REGIONAL TRANSFER17/01/2021 11:15:54 AM

Inter-regional transfer limit variation: Hazelwood - South Morang No 2 500 kV Line (VIC) - Voltage Control

AEMO ELECTRICITY MARKET NOTICE

The Hazelwood - South Morang No 2 500 kV Line has been de-energised to manage voltages in the Victoria region.

The following constraint set was invoked at 1110 hrs 17/01/2021

V-HWSM

The constraint set contains equations with the following interconnectors on the LHS.

T-V-MNSP
V-S-MNSP1
V-SA
VIC1-NSW1

Refer to AEMO Network Outage Scheduler (NOS) for further details

Manager NEM Real Time Operations
     
82196NON-CONFORMANCE16/01/2021 07:30:13 PM

NON-CONFORMANCE Region NSW1 Saturday, 16 January 2021

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Saturday, 16 January 2021

AEMO declared a schedule generating unit non-conforming

Unit: MP1
Duration: 16/01/2021 19:25 to 16/01/2021 19:30
Amount: -25 MW
Constraint: NC-N_MP1

Auto-generated on behalf of Manager NEM Real Time Operations
     
82192RECLASSIFY CONTINGENCY16/01/2021 02:44:55 AM

Cancellation of a Non-Credible Contingency Event: Bulli Creek - Dumaresq 8L 330KV line and Bulli Creek - Dumaresq 8M 330KV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD1

Lines: Bulli Creek - Dumaresq 8L 330KV and Bulli Creek - Dumaresq 8M 330KV

Cancellation time: 16/01/2021 02:44

Constraint set(s) revoked:
I-QNI_ONE_PHASE_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NSW1-QLD1


Refer AEMO Electricity Market Notice 82191

Auto-generated on behalf of Manager NEM Real Time Operations
     
82191RECLASSIFY CONTINGENCY16/01/2021 01:39:25 AM

Reclassification of a Non-Credible Contingency Event: Bulli Creek - Dumaresq 8L 330KV line and Bulli Creek - Dumaresq 8M 330KV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Bulli Creek - Dumaresq 8L 330KV and Bulli Creek - Dumaresq 8M 330KV

Duration: 16/01/2021 01:39 until further notice

Constraint set(s) invoked:
I-QNI_ONE_PHASE_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NSW1-QLD1


Auto-generated on behalf of Manager NEM Real Time Operations
     
82190RECLASSIFY CONTINGENCY16/01/2021 12:29:55 AM

Cancellation of a Non-Credible Contingency Event: Bulli Creek - Dumaresq 8L 330KV line and Bulli Creek - Dumaresq 8M 330KV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD1

Lines: Bulli Creek - Dumaresq 8L 330KV and Bulli Creek - Dumaresq 8M 330KV

Cancellation time: 16/01/2021 00:29

Constraint set(s) revoked:
I-QNI_ONE_PHASE_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NSW1-QLD1


Refer AEMO Electricity Market Notice 82181

Auto-generated on behalf of Manager NEM Real Time Operations
     
82189RECLASSIFY CONTINGENCY15/01/2021 11:54:55 PM

Cancellation of a Non-Credible Contingency Event: Lismore - Dunoon 9U6 132kV line and Lismore - Dunoon 9U7 132kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: NSW1

Lines: Lismore - Dunoon 9U6 132kV and Lismore - Dunoon 9U7 132kV

Cancellation time: 15/01/2021 23:54

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 82185

Auto-generated on behalf of Manager NEM Real Time Operations
     
82188RECLASSIFY CONTINGENCY15/01/2021 10:45:00 PM

Cancellation of a Non-Credible Contingency Event: Hazelwood - Rowville No.1 220kV line and Hazelwood - Rowville No.2 220kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: VIC1

Lines: Hazelwood - Rowville No.1 220kV and Hazelwood - Rowville No.2 220kV

Cancellation time: 15/01/2021 22:44

Constraint set(s) revoked:
V-HWRO_R_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Refer AEMO Electricity Market Notice 82183

Auto-generated on behalf of Manager NEM Real Time Operations
     
82187RECLASSIFY CONTINGENCY15/01/2021 10:35:00 PM

Cancellation of a Non-Credible Contingency Event: Eildon PS - Mt Beauty No.1 220 kV line and Eildon PS - Mt Beauty No.2 220 kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: VIC1

Lines: Eildon PS - Mt Beauty No.1 220 kV and Eildon PS - Mt Beauty No.2 220 kV

Cancellation time: 15/01/2021 22:34

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 82186

Auto-generated on behalf of Manager NEM Real Time Operations
     