116086INTER-REGIONAL TRANSFER11/04/2024 02:57:43 PM

Inter-regional transfer limit variation - Hazelwood - South Morang No. 1 500 kV Line - Vic region - 11/04/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Hazelwood - South Morang No. 1 500 kV Line - Vic region - 11/04/2024

A planned outage of Hazelwood - South Morang No. 1 500 kV Line in the Vic region was scheduled from 0630 hrs 11/04/2024 to 1830 hrs 11/04/2024.

The outage has been completed and Hazelwood - South Morang No. 1 500 kV Line returned to service at 1450 hrs 11/04/2024.

Constraint set revoked: V-HWSM

Manager NEM Real Time Operations
     
116085MARKET INTERVENTION11/04/2024 08:03:17 AM

Possible intervention to manage power system security in SA region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in SA region

The synchronous generating units currently expected to be synchronised in SA from 0830 hrs 12/04/2024 will be inadequate to maintain a secure operating state in SA .
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA .

Manager NEM Real Time Operations
     
116084MARKET INTERVENTION11/04/2024 07:27:24 AM

Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 10/04/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 10/04/2024

Refer Market Notice 116080

The AEMO Intervention Event and all associated directions are cancelled from 0725 hrs 11/04/2024

Manager NEM Real Time Operations
     
116082INTER-REGIONAL TRANSFER11/04/2024 02:28:10 AM

Inter-Regional Transfer limit variation - Directlink - NSW Region

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Directlink - NSW Region

There has been an unplanned outage of the No 3 Leg of Directlink .

The following constraint set was invoked at 0225 hrs 11/04/2024

N-X_MBTE_2

The constraint set contains the following interconnector on the left hand side.

N-Q-MNSP1

Refer AEMO Network Outage Scheduler (NOS) for further details.

Manager NEM Real Time Operations
     
116081MARKET SYSTEMS10/04/2024 06:04:34 PM

CHG0087908 | Completed | Pre-Production | Pre-Prod MSATS Lifecycle Maintenance

Change Number: CHG0087908
Notification issued to: Market Notice

Notification Type: Completed
Change Type: Normal

Service/Component: MSATS - Consumer Administration and Transfer Solution(CATS)_PreProd

Change Title: Pre-Prod MSATS Lifecycle Maintenance
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
116080MARKET INTERVENTION10/04/2024 04:20:46 PM

Direction - SA region 10/04/2024

AEMO ELECTRICITY MARKET NOTICE.

Direction - SA region 10/04/2024

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).

The direction was necessary to maintain the power system in a secure operating state.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1605 hrs on 10/04/2024.

Intervention pricing does not apply to this AEMO intervention event.

Manager NEM Real Time Operations
     
116078POWER SYSTEM EVENTS10/04/2024 03:44:19 PM

Update - Non-credible contingency event - QLD region - 10/04/2024

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - QLD region - 10/04/2024

Refer AEMO Electricity Market Notice 116072

At 1540 hrs the Ingham South to Cardwell 132 kV line was returned to service.

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
     
116077MARKET INTERVENTION10/04/2024 03:19:10 PM

Update - Possible intervention to manage power system security in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Possible intervention to manage power system security in SA region

Refer AEMO Electricity Market Notice 116075

The synchronous generating units currently expected to be synchronised in SA from 1030 hrs 11/04/2024 will be inadequate to maintain a secure operating state in SA .

AEMO estimates that, in the absence of sufficient market response by 1600 hrs 10/04/2024, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
     
116076NON-CONFORMANCE10/04/2024 02:55:14 PM

NON-CONFORMANCE Region QLD1 Wednesday, 10 April 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 10 April 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 10/04/2024 14:35 to 10/04/2024 14:55
Amount: 16 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     