Market Information on Planned Electricity Network Outages

The spreadsheets linked to on this page contain the Planned Electricity Network Outage Information for ElectraNet, TransGrid, SP AusNet and AEMO Transmission services, Essential Energy, Powerlink, Transend, Directlink and Murraylink for the 13 month period from January, 2012.

This information has been provided to AEMO by the TNSPs as required under clause 11.30.2 of the National Electricity Rules and has also been published as an AEMO Communication.  The AEMO Communication also includes a copy of TransGrid’s OM 521 which contains limit equation information for their outages.

Questions regarding specific outages should be directed to the relevant TNSP contact in the first instance:

Powerlink: Kim Lundie, email klundie@powerlink.com.au
TransGrid: Geoff Cook, email Geoff.Cook@transgrid.com.au
AEMO Transmission Services: Michael Redpath, email Michael.Redpath@aemo.com.au
SP AusNet: Lance Robson.  Lance.Robson@sp-ausnet.com.au
ElectraNet SA: Steve Ferdinandy, email ferdinandy.stephen@electranet.com.au
Transend: Alan Wang, email Alan.Wang@transend.com.au
Murraylink and Directlink: Stuart Dodds, stuart.dodds@pipelinetrust.com.au
Essential Energy: John Owens, john.s.owens@essentialenergy.com.au

Clause 11.30.2 requires AEMO to determine and publish an assessment of the projected impact of electricity network outages on intra and inter-regional power transfer capabilities.  AEMO has included limit equations and/or alternate transfer capability information and constraint set IDs in these outage plans.

AEMO has developed a constraint equation conversion tool which allows the user to view "Plain English" descriptions of constraint equations, and has made it available to market participants via the MMS Web (http://mms.prod.nemnet.net.au/Mms/login.aspx). For details on getting access to the tool, please contact the AEMO Helpdesk on 1300 300 295.

Market Participants can obtain the Plain English descriptions for each of the constraint equation(s) associated with a particular outage by copying the Constraint Set ID from the from the  spreadsheets containing Planned Electricity Network Outages into the constraint equation conversion tool.

For questions regarding the limit equation/alternate transfer capability information or plain English descriptions, please contact Sujeewa Rajapakse

DISCLAIMER
  1. Purpose – The Australian Energy Market Operator Limited (AEMO) prepares and publishes information about planned network outages for the sole purpose of complying with a requirement to publish an assessment of the projected impact of electricity network outages on intra-regional and inter-regional power transfer capabilities in accordance with clause 3.7A of the National Electricity Rules.

  2. No Reliance or warranty – This information is provided in a spreadsheet that contains data provided by third parties and might contain conclusions or forecasts and the like that rely on that data. This data is included “as is” and can change at short notice due to operational requirements.  While AEMO has used due care and skill in compiling this information, AEMO does not warrant or represent that the data, conclusions, forecasts or other information in the spreadsheet are accurate, reliable, complete or current or that they are suitable for particular purposes.  You should verify and check the accuracy, completeness, reliability and suitability of the information contained in the spreadsheet for any use to which you intend to put it, and seek confirmation from each relevant provider of this information before using it, or any information contained in it.

  3. Limitation of liability - To the extent permitted by law, AEMO and its advisers, consultants and other contributors to the spreadsheet (or their respective associated companies, businesses, partners, directors, officers or employees) shall not be liable for any errors, omissions, defects or misrepresentations in the information contained in the spreadsheet, or for any loss or damage suffered by persons who use or rely on such information (including by reason of negligence, negligent misstatement or otherwise). If any law prohibits the exclusion of such liability, AEMO’s liability is limited, at AEMO’s option, to the re-supply of the information, provided that this limitation is permitted by law and is fair and reasonable.