Update to NEM load table (Unmetered Loads) – current proposals

Proposal to Update NEM Load Table (Unmetered Loads)

Following the migration from the Jurisdictional Metrology Procedures to the NEM Metrology Procedure, the obligation to update and publish the Load Tables for Type 7 Metering Installations (NEM Load Table) lies with AEMO.

The NEM Load Table sets out the power consumption values for each unmetered device type.  These power consumption values are used in the algorithm that calculates metering data for unmetered loads in the NEM.

As per clause 12.1.4(d) of the NEM Metrology Procedure Part B AEMO is required to:

  • Consider and publish proposals to add an unmetered device type to the NEM Load Table.
  • Take into account the views of interested parties to determine whether to add an unmetered device type to the NEM Load Table.

The following process will be used to amend the NEM Load Table:

  • Publish the supporting documentation for the proposed new unmetered device load value on the AEMO website for comment and agreement by industry.
  • Period for comments on the proposed unmetered device load value will be 20 business days.
  • In the absence of any comments that dispute these proposals, AEMO will take the proposed load for the unmetered device type as agreed.
  • The new unmetered device load value agreed and published in the NEM Load Table may only be used exactly as tested.
  • The new unmetered device load value agreed and published can be used in all NEM jurisdictions that have declared street lights as market loads.

AEMO invites comment as to the acceptance of this new unmetered device load value into the NEM Load Table as per clause 12.1.4(d) of the NEM Metrology Procedure Part B.

Sylvania-Schreder Avento (3) Luminaires


Sylvania-Schreder has applied to have its Avento 75W, 142W and 232W LED Luminaires added to the NEM Load Table as unmetered devices and has proposed the following amendment to the NEM Load Table:

Jurisdiction Submitted by
Unmetered Device
Load as tested (W)
ALL Sylvania-Schreder
Avento 75W 75.6W
ALL Sylvania-Schreder Avento 142W
141.4W
ALL Sylvania-Schreder Avento 232W
233.4W

AEMO has considered the Sylvania-Schreder proposal against the minimum requirements to add new unmetered device types to the NEM Load Table (as set out in clause 12.1.4(d) of the Metrology Procedure Part: B) and concludes that this proposal fulfils these minimum requirements.

The Sylvania Schreder proposal, including supporting test results, technical summary and letter from the City of Salisbury supporting the installation of these devices are published on this web page.

Please direct all comments to David Ripper, Principal Metrology Engineer, NEM.UML@aemo.com.au

Date of publication: 14 March 2024.

Reponses to be submitted by no later than 12 April 2024.

Sylvania-Schreder IZYLUME EVO (10) Luminaires

Sylvania-Schreder has applied to have its IZYLUME EVC (10) LED Luminaires added to the NEM Load Table as unmetered devices and has proposed the following amendment to the NEM Load Table:

Jurisdiction Submitted by
Unmetered Device
Load as tested (W)
ALL Sylvania-Schreder
IZYLUME 35W 35.4W
ALL Sylvania-Schreder IZYLUME EVO 50W
50.6W
ALL Sylvania-Schreder IZYLUME75W
73.3W
ALL Sylvania-Schreder IZYLUME EVO 72W
71.9W
ALL Sylvania-Schreder IZYLUME EVO 73W
72.4W
ALL Sylvania-Schreder
IZYLUME EVO 110W
107.3W
ALL Sylvania-Schreder IZYLUME EVO 149W
147.9W
ALL Sylvania-Schreder IZYLUME EVO 162W
159.7W
ALL Sylvania-Schreder IZYLUME EVO 225W
224.2W
ALL Sylvania-Schreder IZYLUME EVO 249W
251.6W


AEMO has considered the Sylvania-Schreder proposal against the minimum requirements to add new unmetered device types to the NEM Load Table (as set out in clause 12.1.4(d) of the Metrology Procedure Part: B) and concludes that this proposal fulfils these minimum requirements.

The Sylvania Schreder proposal, including supporting test results, technical summary and letter from the City of Port Adelaide supporting the installation of this device are published on this web page.

Please direct all comments to David Ripper, Principal Metrology Engineer, NEM.UML@aemo.com.au

Date of publication: 22 February 2024.

Reponses to be submitted by no later than 22 March 2024.

WE-EF Lighting AFL 130 48W 72W 96W LED Luminaires

WE-EF Lighting has applied to have its AFL 130 48W, 72W and 96W LED Luminaires added to the NEM Load Table as unmetered devices and has proposed the following amendment to the NEM Load Table:

Jurisdiction Submitted by
Unmetered Device
Load as tested (W)
ALL WE-EF Lighting
AFL 130 48 LED 48W/350mA 53.4W
ALL WE-EF Lighting AFL 130 48 LED 72W/500mA
74.7W
ALL WE-EF Lighting AFL 130 48 LED 96W/700mA
103.9W


AEMO has considered the WE-EF Lighting proposal against the minimum requirements to add new unmetered device types to the NEM Load Table (as set out in clause 12.1.4(d) of the Metrology Procedure Part: B) and concludes that this proposal fulfils these minimum requirements.

The WE-EF Lighting proposal, including supporting test results, technical summary and letter from Transport Canberra and City Services supporting the installation of this device are published on this web page.

Please direct all comments to David Ripper, Principal Metrology Engineer, NEM.UML@aemo.com.au

Date of publication: 22 February 2024.

Reponses to be submitted by no later than 22 March 2024.

Pecan Lighting DarkLicht DL 60W LED Luminaire

Pecan Lighting has applied to have its DarkLicht DL-60W LED Luminaire added to the NEM Load Table as unmetered devices and has proposed the following amendment to the NEM Load Table:

Jurisdiction Submitted by
Unmetered Device
Load as tested (W)
ALL Pecan Lighting
DarkLicht DL-60W 62W


AEMO has considered the Pecan Lighting proposal against the minimum requirements to add new unmetered device types to the NEM Load Table (as set out in clause 12.1.4(d) of the Metrology Procedure Part: B) and concludes that this proposal fulfils these minimum requirements.

The Pecan Lighting proposal, including supporting test results, technical summary and letter from the City of Adelaide Council supporting the installation of this device are published on this web page.

Please direct all comments to David Ripper, Principal Metrology Engineer, NEM.UML@aemo.com.au

Date of publication: 1 February 2024.

Reponses to be submitted by no later than 1 March 2024.