This notice informs all National Electricity Market Registered Participants, Metering Service Providers, Intending Participants and interested parties that AEMO is conducting the first stage of National Electricity Market Rules consultation for the Exemption Procedure.
AEMO invites comment on this procedure under consultation.
The procedure has been updated to facilitate the implementation of the AEMC’s Final Rule Determination: National Electricity Amendment (Provision of Metering Data Services and Clarification of Existing Metrology Requirements) Rule 2010. The key features of version 41 of the Rules include:
- The creation of a new service provider category of, Metering Data Provider, including the accreditation, registration and dispute resolution processes to be applied.
- The transfer of responsibility for metering data services to the responsible person for connection points where the Transmission Network Service Provider.. For these connection points AEMO will retain responsibility for the provision of metering data services.
- Creation of service level procedures in the Rules that will apply to Metering Providers and Metering Data Providers.
- Changes to metering data terms for consistent application across the Rules.
- Restructuring of clauses in Chapter 7 to facilitate a more coherent organisation of the Rules pertaining to metrology.
The scope of this consultation relates to
a) consequential update of the Exemption Procedure in respect of the new and changed Rule clauses in chapter 7;
b) amendment to the style and layout of the document text; and
c) changes and amendment of 'language' to remove ambiguity and provide added clarity.
The following table outlines the proposed key dates of consultation process:
|
|
Closing date for submissions received in response to this Notice of First Stage of Rules Consultation |
26 May 2011 |
Publication of the Draft Determination and Report and invitation to make submissions in response to the Draft Determination |
Currently, proposed date is 27 June 2011 |
Closing date for submissions received in response to the Draft Determination and Report |
Currently, proposed date is 19 July 2011 |
Publication of the Final Determination and Report |
Currently, proposed date is 3 August 2011 |
Closing date for submissions in response to this first stage of consultation is 5:00 pm EST on 26 May 2011.
Please direct all responses and comments to Kambiz Vessali at kambiz.vessali@aemo.com.au
Further details regarding this submission and consultation can be found in the Notice of First Stage of Rules Consultation document.
Date of publication: 8 April 2011.
DRAFT DETERMINATION
FIRST STAGE
First Stage Consultation Participant Responses